EPC Project of Qian'an Power Plant
Capacity: 1×220MW
The plant was invested by DaTang International Power Generation Co., Ltd. It adopted power
generation units of 1×220MW for the first stage and was equipped with one 440 tons / hour
Circulating Fluidized Bed Boiler and one 220t/h Circulating Fluidized Bed Boiler.
Desulfurization by adding limestone into the furnace is introduced. The project began in August
2006 and was finished in September 2007, it has won the National Silver Key Prize of EPC
Project. |
 |
EPC project of Gujiao Power Plant
Capacity: 2×600MW
Managed by Shanxi Xingneng Power Generation Co.,Shanxi Gujiao Power Plant has put into production with thefirst stage construction of 2×300MW in 2005. The 2nd stage of 2×600MW direct air-cooled generating sets was invested by Xishan Coal & Power Co., Ltd and Shanxi Hexin Power Development Co., Ltd, Gujiao Power Plant, with the dynamic investment of 4.37 billion RMB.The plant is one of the projects supporting the west-east electricity transmission of the National Tenth Five-year Plan, Balancing the power generation in Shanxi province, and safeguarding the electricity transmission in the long term. Comprehensive utilization of the coal resources leads the plant energy-saving and pollution-reducing, which makes it being considered as a key project by Shanxi provincial government.NCPE won this EPC project through public bidding. |